1.
While performing work on the right of way, contractors must expect trains,
engines, or roadway machines on all tracks, at all times, from any
direction.
Please
type in true or false
(case sensitive).
2.
Any hazardous or waste spill must be promptly reported to the FEC
environmental office.
Please
type in true or false
(case sensitive).
3.
Contractors must obtain permission to perform work in Switching Yards or
Terminals from the General Manager, Trainmaster, or his designee.
Please
type in true or false
(case sensitive).
4.
Job briefings are required prior to starting and again whenever the task or
location changes.
Please
type in true or false
(case sensitive).
5.
Contractors _______ operate
Machines or Equipment on FEC’s right of way, which fouls any track without
being, provided flag protection from trains by a qualified FEC approved
Flagman.
a.
must not
b.
are allowed to
Please
type in the corresponding letter of your choice (case
sensitive).
6.
All Contractors must use proper safety equipment on FEC property.
Please
type in true or false
(case sensitive).
7.
Required
Personal Protective Equipment.
a.
Hi visibility reflective Safety Vest or Hard Hat with reflective
stripe.
b.
Safety Glasses and /or goggles with side shields as required ANSI
Approved
c.
Safety Boots
and Hardhat ANSI approved
d.
All the above
Please
type in the corresponding letter of your choice (case
sensitive).
8.
Contractors must not foul any track
within 4 feet of the rail side without being provided flag protection from
trains by a qualified FEC approved Flagman.
Please
type in true or false
(case sensitive).
9.
Prior to performing any excavation on FEC right of way, permission must be
obtained from the engineering office.
Please
type in true or false
(case sensitive).
10.
When in doubt, always take the safest course of action.
Please
type in true or false
(case sensitive).
11.
A policy of ZERO tolerance for unsafe work practices is in full force and
violation of these rules will result in
all work being stopped until compliance is reached.
Please
type in true or false
(case sensitive).
12.Contractors
must restore any disturbed surfaces
to their original condition prior to leaving the work site. Safeguarding for
safety hazards must be provided and the Railway notified of any potentially
hazardous conditions are created, to include location and type of condition.
Please
type in true or false
(case sensitive).
13.
Contractor vehicles or Machinery parked or stored on the right of way must
be positioned as far as possible from the rail side.
Please
type in true or false
(case sensitive).
14.
The possession of drugs or alcohol is permitted while on FEC property.
Please
type in true or false
(case sensitive).
15.
All Incidents Accidents resulting
in injuries or damage to railway property or equipment must be reported to
the immediately be reported to the FEC Dispatchers office at 1-800-342-1131
ext.2302
Please
type in true or false
(case sensitive).
16.
Contractors must have an ________ agreement to enter FEC property.
a.
Established
b.
Verbal
c.
Common
Please
type in the letter of the correct answer
(case sensitive).
17.
Avoid walking closer than ____ feet
from the field side of the rail. When
it is necessary to perform your task in proximity to the rail, be aware and
expect movement on any track, from any direction, at any time.
a.
9
b.
4
c.
20
Please type in the letter of the correct answer
(case sensitive).
18.
All excavations must meet OSHA Confined space/entry standards when
applicable.
Please
type in true or false
(case sensitive).
19.
Possession of weapons is permitted on the company property.
Please
type in true or false
(case sensitive).
20.
Fall Protection must be utilized and must comply with requirements of both
OSHA and the FRA.
Please
type in true or false
(case sensitive).
21. If you are required to work in
the field at any time, footwear that meets the following requirements must
be worn. High top (6 inches or
more), Lace up type.
Please
type in true or false
(case sensitive).
22. You must wear hearing
protection when you are: Within
100 feet, or 2 car lengths, of a locomotive under load.
Riding inside a locomotive under load.
Working in high noise environment.
In locations posted with hearing protection required signs.
Where required by supervisor. Please
type in true or false
(case sensitive).
WHEREAS,
is
obtaining this orientation and any of the materials provided for
certain of its employees who work on or about railroad equipment, and
WHEREAS, THE FLORIDA EAST COAST RAILWAYS,
hereinafter called "FEC", is willing to provide this orientation and
any of the materials provided, but only upon the following terms and
conditions, NOW THEREFORE, it is agreed as follows: In consideration of this
orientation and any of the materials provided to the management of
your company or you as an individual for their internal use by you,
hereby assume all risk of and agrees to indemnify and hold FEC and the
administrator of this site harmless
from any personal injury to or death of its officers, agents and employees,
and loss of or damage to property in its or their custody or possession,
which shall in any manner arise from or be alleged to be due to in, in whole
or in part, this orientation or materials provided to its employees by FEC,
EXCEPT TO THE EXTENT SUCH INJURIES OR DAMAGES BE CAUSED BY OR
CONTRIBUTED TO BY THE INTENTIONAL MISCONDUCT OR GROSS NEGLIGENCE OF
FEC, ITS OFFICERS, EMPLOYEES, AGENTS, OR ANY THIRD PARTY.
FEC is hereby released and forever discharged, as well as its
subsidiary and affiliated companies, and the officers, agents, and employees
of said companies, from all claims, liabilities, and costs of every kind by
reason of any such injury to or death of persons and loss of or damage to
property. This Release shall be binding
upon the submission of this document.
I
understand that by submitting my name and, as applicable, the names of the other individuals
who have completed this orientation
section, I am indicating that these personnel have
actually completed this section of the orientation and understand this document. I am
an officer of the corporation named above, who is duly authorized and fully
empowered by said corporation to execute the same on its behalf or myself as
an individual.
If
you receive an error message when you submit your answers, you can email
your answers to the Webmaster for processing.
NOTE:
If you do not receive your course completion card within 10 working days
please email our office. webmaster@contractororientation.com